January 2021:
Connecting business and engineering, Rustandy Building officially opens
October 2020:
The University of baby直播app Business and Engineering project is coming along nicely and will be completed near the end of the year. The two new air handler units are going to start up and later this month. That will kick off our commissioning process that verifies that everything is operating and functioning correctly. The new Engineering Auditorium will be a great space for the University. We just installed the carpeting at the tiered seating levels and installed the fixed tables in this area. In the Business school the woodwork is starting at the Innovation Hub seating area that connects to the new Business school Caf茅. On the exterior of the project the landscaping is in progress and the west Engelbretson鈥檚 Quad will have sod replaced in the upcoming weeks.
March 2020:
Engineering Level 1B
- Install tables
- East drywall patch back
- Furniture setup
Engineering Level 1
- Ceiling grid
- Vents/diffusers
- Floor prep Engineering
Roof/Auditorium
- Fire proofing
- Install precast cladding
- Wall framing
- Parapet backing
Business Level 1
- Mechanical, electrical and plumbing (MEP) trim out
- MIllwork
- Flooring
Business Level 2
- Ceiling grid
- MEP trim out
Business Level 4
North Expansion
- East weather barrier
- West windows install
- MEP OH 2nd and 3rd floors
- Priority walls 4th floor
West Expansion
- Drywall
- Tape and finish
- Paint
- Set air handler
- Complete structure at air handler
February 2020:
Engineering Level 1B
- Install tables
- East drywall patch back
- Furniture setup
Engineering Level 1
- Ceiling grid
- Vents/Diffusers
- Floor prep
Engineering Roof/Auditorium
- Fire proofing
- Install precast cladding
- Wall framing
- Parapet backing
Business Level 1
- Mechanical, electrical and plumbing (MEP) trimout
- Millwork
- Flooring
Business Level 2
- Ceiling grid
- MEP trim out
Business Level 4
North Expansion
- East weather barrier
- West windows install
- MEP OH 2nd & 3rd Floors
- Priority Walls 4th Floor
West Expansion
- Drywall
- Tape and finish
- Paint
- Set air handler
- Complete structure at air handler
January 14, 2020:
The Business and Engineering Project recently completed structural steel erection and is now working on building envelope systems and interior constriction. Interior renovations in of both Business and Engineering are well under way. The project is working to open the fully renovated business library along with 3 new 90 seat classrooms for fall semester 2020. The remainder of the project will turn over in December 2020.
January 2020:
Engineering Level 1B:
- Flooring Install
- Punchlist
- Owner move-in west
Engineering Level 1:
- Drywall
- Tape and finish
- Paint
Engineering Roof/Auditorium:
- Complete structural steel
- Pour floor slabs
- Scaffolding/temporary protection
- Fireproofing
Business Level 1:
- Mechanical, electrical and plumbing (MEP) trimout
- Millwork
- Flooring
Business Level 2:
- Ceiling grid
- MEP trim out
Business Level 4:
- Structural demolition
- Preparation for steel
North Expansion:
- Complete fire proofing
- Weather barrier
- Window installation
West Expansion:
- Frame walls
- MEP wall rough
December 2019:
Engineering Level 1B:
- Doors and hardware
- Final paint
- Grid and ceiling tile patch as needed
Engineering Level 1:
- Wall framing and inspections
- Mechanical, electrical and plumbing (MEP) wall rough-in and inspections
- Overhead MEP installation
- Pulling wire
- Brace frame columns
- Drywall
- Tape and finish
Engineering Roof/Auditorium:
- Layout for new structural steel
- Snow removal
- Remove roofing for new structural steel
- Temporary roof patching
- Demo of concrete window hoods for new structural steel
Business Level 1:
- MEP trimout
- Millwork
- Flooring
Business Level 2:
Business Level 4:
North Expansion:
- Provide temp weather protection with plastic on building
- Install temporary hydronic heat
- Interior fireproofing
- Complete east exterior framing
- Sheath exterior skin east and west
West Expansion:
- Fireproof structural steel
- Priority walls
- Underdrain system
- Overhead mechanical
November 2019:
Engineering Level 1B:
- Doors and hardware
- Wall and ceiling mechanical, electrical and plumbing (MEP) trim
- Prime and paint
- Grid and ceiling tile
- Brace frame columns
Engineering Level 1:
- Wall framing and inspections
- MEP wall rough-in and inspections
- Overhead MEP installation
- Begin pulling wire
- Brace frame columns
Engineering Roof/Auditorium:
- Layout for new structural steel
- Remove roofing for new structural steel
- Demo of concrete window hoods
Business Level 1:
- Drywall hard lids
- Tap/finish hard lids and prime/paint
- Complete ceiling grid
- Begin MEP trim out
Business Level 2:
- Prime and paint first coat
- Frame soffit and hard lids
- Ceiling grid
Business Level 4:
- Pre-planning for demolition
North Expansion:
- Provide temp weather protection with plastic on building
- Install temporary hydronic heat
- Interior fireproofing
- Install clips and framing for exterior skin
- Sheath exterior skin west
West Expansion:
- Install structural steel
- Pour slab on metal deck
- Fireproof structural steel
October 2019:
Engineering Level 1B:
- Doors and hardware
- Wall mechanical, electrical and plumbing (MEP) trim
- Prime and paint
- Grid and ceiling tile
- Brace frame columns
Engineering Level 1:
- Install new brace frames
- Remove walls required for new brace frame connection details
- Re-build walls
Engineering Roof/Auditorium:
- Layout for new structural steel
- Remove roofing for new structural steel
Business Level 1:
- Drywall hard lids
- Install ceiling grid
- Install/adjust fire sprinkler system
- Tape and finish drywall
- Prime and paint first coat
- Coffee bar install
Business Level 2:
- In-wall MEP inspections
- Backing
- Drywall
- Tape and finish drywall
- Prime and paint first coat
Business Level 4:
- Pre-planning for demolition
North Expansion:
- Install penetrations and hanger on decks for electrical, plumbing and ductwork
- Pour floor decks
- Exterior fireproofing
- Layout and clips for exterior fireproofing
West Expansion:
- Complete underground drainage systems
- Grade and install gravel on slab
- Install underground electrical boxes
- Pour slab on grade
- Begin structural steel columns and beams
September 2019:
Engineering Level 1B:
- Metal stud framing
- In-wall mechanical, electrical and plumbing (MEP)
- Overhead MEP
- Drywall and finish
- Brace frame columns
Engineering Level 1:
Business Level 1:
- Frame hard lids
- Backing
- Drywall and insulation
- Tape and finish
- In-wall MEP
- Overhead MEP
- MEP insulation
- Coffee bar MEP rough-in
Business Level 2:
- Framing walls
- In-wall MEP
- Overhead MEP
- MEP insulation
Business Level 3:
- Level 3 ceiling/carper/base demolition
- Crack filler abatement
Business Level 4:
- Framing demolition
- Protection of existing finishes
North Expansion:
- Placement of structural columns and beams
- Floor decking
- Structural detailing
- Safety handrail
West Expansion:
- Blindside waterproofing
- Pier caps
- Shotcrete foundation wall
July 10, 2019:
Engineering Level 1B:
- Micro piles or ongoing at both sides of the floor
- Sawcut concrete, demo, excavate for pier capsat both halves of the floor
- Rebar and concrete work to start later in the month
Business Level 1:
- Demo of walls, ceilings, fixtures and all mechanical, electrical and plumbing (MEP) as required
- MEP and wall layout
Business Level 2:
- Demo of walls, ceilings, fixtures and MEP as required
North expansion:
- Grade beams
- Elevator slab
- Cross brace mat slabs
West expansion:
- Demo of bridge
- Lag and beam
- Excavating for building
- Relocate fiber lines
June 24, 2019:
Construction is underway including the following:
- Site utility and building foundations
- Interior abatement and demolition in Koelbel north end and library.
- Interior abatement, demolition, and structural modifications to support the auditorium / new second floor in the Engineering Center.
March 19, 2019:
It is almost time for construction to begin! Construction fencing will go up over spring break, the week of March 25. Pedestrian detours will be put in place at that time. Initial construction work will include utilities and other site work, with work on the buildings and addition to ramp up after the spring semester.